Renovation. Leeming.

Renovation. Leeming.

Full kitchen, main floor tiling, bathroom and laundry renovation carried out in two stages for a house in Leeming.

Project scope:

Full scale renovation including:

  • Plumbing: Disconnection, reconnection and final fit off
  • Electrical: Disconnection, reconnection and final fit off
  • Demolition and building works: Old brick oven stack and pantry removal, plus building works to achieve new layout
  • New cabinetry and stone: Cabinets and bench top installation
  • Tiling: Splashback

Unique solutions:

Stage 1: Kitchen, bathroom and main floor tiling.

Stage 2: Laundry.

Customer wanted to open up both the kitchen and bathroom, increasing space and making the rooms more fit for purpose. This was achieved in the kitchen by removing the old 1980s style brick oven stack and pantry, while in the bathroom we deleted the bath, which allowed for a much bigger vanity.

Project process:

  1. Skip bin hire
  2. Disconnection of plumbing and electrical services
  3. Demolition
  4. Wall removal
  5. Building works
  6. Floor tiling
  7. Installation of cabinetry and stone
  8. Tiled splashback
  9. Reconnection of plumbing and electrical services
  10. Final clean

CLIENT:
Residential

PARTNERS INVOLVED:
Jewelbic Brothers

PROJECT DURATION:
8 weeks

WORK TYPE:
Kitchen
Bathroom
Laundry
Tiling