Renovation. Scarborough.

Renovation. Scarborough.

Bathroom, laundry and toilet renovation for an apartment in Scarborough.

Project scope:

Full scale renovation of each room including:

  • Skip bin hire: Delivery and collection
  • Demolition: Including rubber mats to protect flooring
  • Plumbing: Disconnection and moving of services, final fit off
  • Electrical: Disconnection and moving of services, final fit off
  • Tiling: Tiling, grouting and silicone
  • Custom cabinetry and stone: Measure, supply and installation
  • Shower screens: Measure, supply and installation
  • Patching: Render wall patching

Unique solutions:

  • Frameless shower screen for a more modern and seamless look
  • Shower and bath niche for added detail and a place to store shampoo, shower gel and the like

The process:

  1. Skip bin hire: Delivered 1-2 days prior to project start date
  2. Demolition: A standard bathroom takes 1-1.5 days to rip out, depending on the amount of existing tiles, the amount of screed and the quality of the glue used to the fasten tiles. This figure includes rubber floor protection mats. This North Perth renovation was no exception.
  3. Plumbing:
    • Disconnection on morning of day 1
    • Moving of services carried out on day 2
    • Final fit off took place upon completion of tiling, custom cabinetry and stone installation – this is standard
  4. Electrical:
    • Disconnection on morning of day 1
    • Moving of services carried out on day 2
    • Final fit off was carried out in the same fashion as the plumbing
  5. Tiling prep work: Concreting, screeding and waterproofing all carried out after moving of plumbing and electrical
  6. Custom cabinetry and stone:
    • Measured on site before commencement
    • Supply and installation after the floor screed has been installed and before the tiling starts
  7. Shower screens:
    • Measured once tiling is 3/4 complete
    • Supply and installation approximately 5-7 days from the measure
  8. Patching: Render wall patching once most of the trades have completed their work
  9. Tiling: Tiling, grout and silicone
  10. Professional cleaning

CLIENT:
Residential

PARTNERS INVOLVED:
Jewelbic Brothers

PROJECT DURATION:
Late-August – mid-October 2021

WORK TYPE:
Bathroom
Laundry
Separate toilet

AGE OF DWELLING:
1960s single storey apartment